MPs ask question after question about Haarlem track maintenance. The only one that matters: is it still worth it?

Dutch Members of Parliament have submitted 38 questions to State Secretary Annet Bertram regarding the canceled joint railway maintenance in Haarlem. The project's failure has resulted in a 60 million euro cost to the state and significant delays, though local officials remain skeptical about whether these inquiries will lead to improvements.